Prior to starting construction, written notice of intent must be submitted how many days in advance?

  1. 5 working days

  2. 10 working days

  3. 15 working days

  4. 30 working days

The correct answer is: 10 working days

The requirement for submitting a written notice of intent prior to starting construction is essential for ensuring that all stakeholders, including regulatory agencies and neighboring property owners, are informed of upcoming construction activities. Submitting the notice 10 working days in advance allows sufficient time for any necessary reviews or approvals, while also giving affected parties the opportunity to respond or voice any concerns they may have regarding the construction project. This timeframe helps foster transparency and communication within the community, and it is a critical step in maintaining compliance with local regulations and ordinances. The other options represent different timeframes that are either too short or unnecessarily long for the typical notification process within the construction industry, making 10 working days the most appropriate requirement for balance and efficiency.