What is the purpose of progress payments in a contract?

  1. To provide upfront costs before work begins

  2. To ensure the contractor follows a planned schedule

  3. To cover unforeseen expenses

  4. To distribute bonuses for quality work

The correct answer is: To ensure the contractor follows a planned schedule

The purpose of progress payments in a contract is primarily to ensure that the contractor adheres to a planned schedule. Progress payments are made at various stages of a construction project as predetermined milestones are met. This structure not only provides a mechanism for cash flow to the contractor but also acts as a motivator to stay on schedule. It allows the contracting party to assess ongoing work quality and adherence to timelines, thereby minimizing the risk of delays and encouraging timely completion of the project. In this context, progress payments contribute to maintaining an organized workflow, facilitating communication between the contractor and the client, and allowing for corrective measures if the project strays from the planned schedule. Ultimately, this approach helps ensure that the project remains on track and is completed according to the agreed-upon timeline.