Which scheduling method uses specific dates to link project tasks?

  1. Bar chart scheduling

  2. Calendar Scheduling

  3. Critical Path Scheduling

  4. Float Scheduling

The correct answer is: Calendar Scheduling

Calendar scheduling is a method that utilizes specific dates to establish a timeline for project tasks. This approach provides a visual representation of the project schedule, allowing project managers and team members to clearly see when tasks are to be started and completed. By assigning tasks to particular dates, calendar scheduling enhances communication among the project team, ensuring that everyone is aware of deadlines and timelines. In calendar scheduling, the focus is on the actual calendar dates, making it straightforward to manage dependencies and sequences of tasks. This technique is particularly beneficial for projects that require precise timing and coordination among multiple tasks, as it highlights date-specific deadlines and milestones. While bar chart scheduling also conveys task durations visually, it does not always specify the exact dates for each activity. Critical path scheduling identifies the longest sequence of dependent tasks to determine the shortest possible project duration but relies more on the relationships between tasks rather than specific dates. Float scheduling deals with the leeway or flexibility in scheduling tasks but does not link tasks to specific dates. Thus, calendar scheduling stands out as the method that explicitly incorporates specific dates to link project tasks effectively.